Home Site Map LOf Web shop Contact

New Studio News Desk Reports

Radio Heatherwood History News Desk Year 2000

New Studio Reports Special ( Studio Construction Progress ).

bullet

Studio Two Test Transmission

On Sunday 17th December Studio Two broadcast a test service of the sustaining service radio two. This milestone in the re-build of the new facilities paves the way for the second studio to be used for on-air services as well as training for new staff.

 Back to Top

bullet

New Studio Update 7th October 2000

The Radio station gears itself up this week with the news that on Tuesday 17th October Radio Heatherwood will resume broadcasting after a three month break. Work has progressed sufficiently to re-launch our services from the new Studio One.

The new studio complex although complete on the outside has still a major amount of work to be completed. Studio Two is unlikely to be ready for use until the new year.

Back to Top

bullet

 New Studio Update 17th September 2000

The station engineer returned from holidays and spent time this week ensuring the temperature in Studio One will be manageable. Windows have been covered with reflective screen. Visual indications of studio power up, has been completed and work is progressing on a move towards on-air date. The league of friends has spent over £2000 so far on the studio move. And the studio engineer has completed 163 hours on the project.

Back to Top

bullet

 New Studio Update 19th August 2000

A busy week completed this week by the station engineer who has been working eight hours a day to make a dent into all the work required to put Radio Heatherwood back on air.

On holiday from his day time occupation, station engineer PJ Davidson-Smith has put up all the transmission lights, completed all cable links to the working studio’s and installed all equipment in studio one.

As part of the new studio build, Bedhead radio system on the Emi unit, has finally been re-instated after many years of no service on the bed-heads wards 11,12,14 are now directly linked to the new studio complex. Connections completed this week.

Radica Broadcast Systems visited this week and the am transmission rack was moved to the new studio complex and is now working in the new location.

Library CD racks were installed this week and all Cd’s are now in order ready to be used.

Back to Top

bullet

 New Studio Update 12th August 2000

Work commenced this week on the wiring in the new equipment room. A dedicated room set aside to carry all transmission equipment for the studio’s. Radio Heatherwood’s phone system was installed this week and messages from either the direct line or the internal extension can be answered by the answer machine.

Back to Top

bullet

New Studio Update 5th August 2000

Radio Heatherwood vacated it’s old premises today. The last of the equipment and records & CD’s were moved to the summer-house( New Studio ). In addition the bedhead amps were also moved to the new room and have been re-connected to the bedhead system. The only item left in the old rooms the am transmitter due for removal on the 15th August.

Back to Top

bullet

New Studio Update 29th July 2000

A busy day for the station manager as the first of the records and equipment is moved to the new premises. The Album library and a small selection of singles have been moved to the new location.

Back to Top

bullet

New Studio Progress Report 15th July 2000

This week’s progress shows the floor covering has been laid in the reception, and painting of the outside exterior is well under way. Final work on the building by the estates will be completed this coming week.

Internal telephone point has now been provided and light fittings have been completed with the installation of their reflectors.

Back to Top

bullet

New Studio Progress Report 8th July 2000

Radio Heatherwood staff continued their cabling work. Mains cables for on-air lights were installed this week. The studio two console frame has been installed along with the installation of the tea making facilities.

The current studio’s are looking rather sad now, with the removal of all the memorabilia from the walls and the removal of the tea facilities.

Back to Top

bullet

New Studio Progress Report 1st July 2000

This weeks progress shows all painting complete and worktops installed. Internal windows have been installed and arrangements for own power supply are nearing completion.

Radio Heatherwood staff were able to gain access this week and work has started on installing data network and phone points.

Back to Top

bullet

New Studio Progress Report 24th June 2000

This week’s report confirms the completion of the installation of the suspended ceiling. In addition this week we have noted the library racks are all complete and ready for painting. Lighting is installed in ceiling grid waiting to be connected. Wheelchair access ramp to new front door has also completed.

The first indications the rooms will be used as a radio studio are in evidence with the move into place of the wooden console structure for the new studio 1.

Back to Top

bullet

New Studio Progress Report 17th June 2000

A visit to the new studio’s today indicates a completion of the walls in both studios’ with the soundproofing pegboard. The new album rack has been constructed and work is progressing on the new singles rack. All doors have been fitted and primary paint coat has been applied. Suspended ceiling is under construction and will be complete this coming week.

Back to Top

bullet

New Studio Progress Report 27th May 2000

The work has progressed this week with the removal of all old light fitting wiring and the installation of some power point wiring in new wall structure for studio 2. In addition access doorway for storage room has been made.

An oversight shows all windows have been boarded up on the external fascia. This has been noted and a correction is due to be made. New external door has been fitted.

Discussions with electricians this week to finalize some details of the power point locations and console power arrangements.

Back to Top

bullet

New Studio Progress Report 20th May 2000

All Windows have been boarded up and fire exit has been removed.This is the first visible signs that work has commenced on the new studio's.

Work commenced in May 2000 on the new studio's.

  

 

Back to Top

 

 

News Desk
Archives

New Studio Progress

Studio Two Test

 

 Studio October 2000

 

Studio September 2000

 

Studio August 2000

 

Studio July 2000

 

Studio June 2000

 

Studio May 2000

 

Back to Top

 

 

Radio Heatherwood is the broadcasting service of the League of Friends Charity No ( 900282 )

League of Friends

© League of Friends Heatherwood 2000 Last Update 10/08/2008